Project Description:
As part of a general trades package, Tooles Contracting Group self-performed all the concrete work which included foundations, pits and slabs for the 265,000 square foot body shop and lab space additions, including demolition, excavation and concrete pours and floor finishing using a laser screed. All work was performed while the plant was still operational and both construction and assembly were not interrupted.
CCC was the construction manager on the $34 Million 265,000 square-foot body shop expansion, a 27,500-square foot Metrology Center, and a brand new 34,000 square foot Center for Technical Vehicle Validation (CTVV) lab.